S.C. Ecorec S.A. and Dombrovschi v. Romania

European Court of Human Rights · 24 January 2023 · Violation

S.C. Ecorec S.A. and Dombrovschi v. Romania is a Committee judgment of the European Court of Human Rights delivered on 24 January 2023 (application no. 31237/14). The Court found a violation of Article 6 (right to a fair trial). The decision was unanimous. HUDOC classifies its importance as: level 3 (low).

Read the full judgment on HUDOC →

Case details

CourtEuropean Court of Human Rights, Committee
Respondent stateRomania
Judgment date24 January 2023
Application no.31237/14
ECLIECLI:CE:ECHR:2023:0124JUD003123714
OutcomeViolation
Violation ofArticle 6 (Right to a fair trial)
No violation ofNone
Articles concernedArticle 6 (Right to a fair trial)
Importance (HUDOC)Level 3 (low). Applies existing case law, of limited legal interest.
VoteUnanimous
Separate opinionsNo

What the case is about

The applicant company is a waste management enterprise which operated a major landfill near Bucharest. The applicant was the applicant company’s general manager and one of its owners.

The Court's ruling

The operative provisions of the judgment, quoted from the official text:

Declares the complaints under Articles 6 and 13 of the Convention and Article 1 of Protocol No. 1 to the Convention concerning the enforcement of the seizure measure imposed on the applicants admissible and the remainder of the application inadmissible;
Holds that there has been a violation of Article 6 of the Convention;
Holds that there is no need to examine the merits of the remaining complaints;
Holds that the finding of a violation constitutes in itself sufficient just satisfaction for any non-pecuniary damage sustained by the applicants on account of the lack of access to court to contest the enforcement of the seizure measure;
Holds
(a) that the respondent State is to pay the applicant company, within three months, EUR 10,000 (ten thousand euros) plus any tax that may be chargeable to the applicant company, in respect of costs and expenses, to be converted into the currency of the respondent State at the rate applicable at the date of settlement;
(b) that from the expiry of the above-mentioned three months until settlement simple interest shall be payable on the above amount at a rate equal to the marginal lending rate of the European Central Bank during the default period plus three percentage points;
Dismisses the remainder of the applicants’ claim for just satisfaction.
© ECHR-CEDH. The original signed text held by the Court is the authentic version. Full text on HUDOC

Judges

Tim Eicke, Faris Vehabović, Branko Lubarda

Language versions on HUDOC

English · French

Official versions are English and/or French. Other languages are translations published on HUDOC.