Superwood Holdings Plc and Others v. Ireland

European Court of Human Rights · 8 September 2011 · Violation

Superwood Holdings Plc and Others v. Ireland is a Chamber judgment of the European Court of Human Rights delivered on 8 September 2011 (application no. 7812/04). The Court found a violation of Article 6 (right to a fair trial). The main finding was adopted by six votes to one. HUDOC classifies its importance as: level 3 (low).

Read the full judgment on HUDOC →

Case details

CourtEuropean Court of Human Rights, Chamber
Respondent stateIreland
Judgment date8 September 2011
Application no.7812/04
ECLIECLI:CE:ECHR:2011:0908JUD000781204
OutcomeViolation
Violation ofArticle 6 (Right to a fair trial)
No violation ofNone
Articles concernedArticle 6 (Right to a fair trial), Article 41 (Just satisfaction)
Importance (HUDOC)Level 3 (low). Applies existing case law, of limited legal interest.
VoteSix votes to one
Separate opinionsNo

The Court's ruling

The operative provisions of the judgment, quoted from the official text:

1. Declares by a majority the applicant companies’ complaint concerning the excessive length of the proceedings admissible and the remainder of the application inadmissible;
2. Holds by six votes to one, that there has been a violation of the reasonable time requirement of Article 6 § 1 of the Convention as regards the applicant companies;
3. Holds by six votes to one,
(a) that the respondent State is to pay the applicant companies, within three months from the date on which the judgment becomes final in accordance with Article 44 § 2 of the Convention, the amount of EUR 3,800 (three thousand eight hundred euros), inclusive of VAT plus any other tax that may be chargeable, in respect of costs and expenses of the Convention proceedings; and
(b) that from the expiry of the above-mentioned three months until settlement simple interest shall be payable on the above amount at a rate equal to the marginal lending rate of the European Central Bank during the default period plus three percentage points;
4. Dismisses unanimously the remainder of the claim for just satisfaction.
© ECHR-CEDH. The original signed text held by the Court is the authentic version. Full text on HUDOC

Judges

Dean Spielmann, Elisabet Fura, Karel Jungwiert, Mark Villiger, Isabelle Berro-Lefèvre, Ann Power, Ganna Yudkivska

Cited by later judgments (7)

Language versions on HUDOC

English · French

Official versions are English and/or French. Other languages are translations published on HUDOC.